SYSTEM OVERVIEW
Zakum Development Company operate a large Crude Separation and Stabilisation Plant on “Zirku Island” which is located in the Arabian Gulf, about 135km Northwest of mainland Abu Dhabi city.
The plant area on Zirku is divided into two sections the Plant area is known as Part A while the Non-Plant area is called part B. GAI-Tronics was approached to bid for the replacement of the existing Island PA System which had been installed in the 1980’s. GAI-Tronics has already supplied and installed PA Systems on Zakum’s remote North, East, South & West Satellite Offshore Oil Installations which feed the Zirku Island complex with Oil for processing and distribution. The project required a phased installation with the complete system for both locations being designed and manufactured synchronously.
The system will cover the entire Island including the following locations:- Airport, Jetty, Plant Areas, Indoor & Outdoor Cinemas, Mosque, Construction Camp, Amenity Centre & Liwa Housing.
|